Client: Westar Energy
Project Date: October 2013 to June 2014
Man Hours: 25,734
Designed and built a new process building to house a new clarifier and process equipment used for removing sulfate from the plant’s FGD wastewater. Wolf worked hand in hand with a Chemical Engineering firm to tie the new Sulfate Removal System into their existing Wastewater treatment facility.
Wolf self-performed the following:
• Piping – Wide Varity of Specialty Pipe
• Millwright – Equipment Setting & Fabrication
• Concrete – Design and Install of Building and Equipment Foundations (w/ Certus)
• HVAC
• Metal Building Erection
• Structural Steel Erection
• Managed Electrical Design and Install